Current projects by department:

  • Building
    • Currently no projects
  • City Manager/Administration
    • Currently no projects
  • Public Works
    •  N. Professor Street ImprovementsView Invitation to Bid
      • The project is located on N. Professor St. between College St. and Lorain St. within the City of Oberlin, Ohio and consists of milling approximately 2,107 SY of asphalt pavement and installing 3.25″ of new asphalt and pavement overlay mat. Bid items are included for full depth repairs to be determined after milling. The project includes approximately 82 LF of Type 6 concrete curb removal and replacement with new curb and underdrain. The project also includes the installation of 88 LF of 12 inch RCP storm sewer, installation of 2 new catch basins, a new shallow Storm Sewer, removal of a brick MH replaced with a new precast Manhole, and other incidentals. The project includes constructing a raised brick crosswalk and a brick crosswalk at grade. The project includes sidewalk, ramps, pavement markings, lawn restoration, and regrading to new curb height.The probable construction cost has been determined to be $147,700. Bids due on June 19, 2018. “Notice to Proceed” is anticipated to be issued on or before July 13, 2018. The substantial completion date for the project is August 24, 2018. The final completion date for the project is September 8, 2018.
    • Oberlin-Elyria Road Pavement ImprovementView Invitation to Bid
      • The project is located on Oberlin-Elyria Rd between Parsons Rd. and RT 511. within the City of Oberlin, Ohio and consists of milling approximately 3,797 SY of asphalt pavement at 2” depth, and installing 3.25″ of new asphalt and pavement overlay mat. Bid items are included for full depth repairs to be determined after milling. The project includes restoration of an asphalt drive apron, shoulder reconditioning, pavement markings, and signage.The probable construction cost has been determined to be $177,661. Bids due on June 19, 2018. “Notice to Proceed” is anticipated to be issued on or before July 13, 2018. The substantial completion date for the project is September 6, 2018. The final completion date for the project is September 21, 2018.
    • Lincoln Street Improvements – View Invitation to Bid
      • The project is located on Lincoln St. between Hamilton St. and S. Professor St. within the City of Oberlin, Ohio and consists of milling approximately 9,030 SY of asphalt pavement and installing 3.25″ of new asphalt and pavement overlay mat. Bid items are included for full depth repairs to be determined after milling. The project includes removing approximately 7,740 LF of existing Type 3 concrete curb and replacing with new ODOT Type 2 concrete curb with underdrain. The project also includes the installation of 155 LF of 12 inch RCP Storm sewer connecting catch basins, and includes removal of existing structures and installation of 10 catch basins, and other incidentals. Sanitary sewer rehabilitation includes replacing five (5) sanitary sewer manholes with new precast concrete sewer manholes, the installation of a new manhole, rehabilitation of six (6) MH tops including new castings and chimney seals. removing and replacing 156 total feet of 8” Sanitary sewer. The project includes restoration of gravel, asphalt, and concrete drive aprons, sidewalk, pavement markings, lawn restoration, and regrading to new curb height.The probable construction cost has been determined to be $804,495. Bids due on June 19, 2018. “Notice to Proceed” is anticipated to be issued on or before July 13, 2018. The substantial completion date for the project is October 26, 2018. The final completion date for the project is November 10, 2018.
    • Sidewalk Repair Program 2018View Invitation to Bid
      • Contract 2018-06 2018 Sidewalk Repair ProgramThis project is to do various sidewalk repairs throughout the City of Oberlin.Individual quotes are requested for:
        1) Walk removal and replacement with new concrete walk
        2) Concrete walk leveling by resetting or by “mudjacking”
        3) Concrete edge grinding.The City may elect to award some, all or none of these bid items and may award each item to the same or multiple contractors.1) Concrete removal and replacement consists of removing and replacing 8,016 sf of 4” walk, 10,29 sf of 6” wire reinforced walk, and 272.5 sf of 9” wire reinforced walk.
        2) Concrete slab leveling consists of 817 sf of sidewalk slabs to be leveled.
        3) Grinding consists of 217 lf of grinding.The engineer’s probable construction cost for the four scopes of work has been determined to be $100,895 for Concrete Repair Work; $6,488 for Concrete Slab Leveling; $7,025 for Concrete Grinding.There will be a non-mandatory prebid meeting in the Municipal Building, 85 South Main Street, Oberlin, Ohio 44074, at 4:00 p.m., June 12, 2018. Bids are due 10:00 a.m. on June 19, 2018. “Notice to Proceed” is anticipated to be issued on or before July 13, 2018. The substantial completion date for the project is October 16, 2018. The final completion date for the project is October 31, 2018.
    • Safe Routes to School View Invitation to Bid
      • This project includes the installation of approximately 5,660 lineal feet of new sidewalks, accessible ramps and crosswalks at eleven (11) locations and the installation of one (1) School Zone Flasher System on Prospect St. in the City of Oberlin. Bids due on April 4, 2018
  • OMLPS
    • Currently no projects
  • Planning & Economic Development/Housing
    • Currently no projects
  • Recreation
    • Currently no projects